- Applicant is responsible for locating all private underground facilities prior to commencing any excavation on the property. OG&E and its contractors are not responsible for damage to private facilities that were not located or improperly located.
- Applicant is responsible for backfill compaction, removal of rock and other debris remaining after excavation, and replacement of sod or other landscaping features.
- Pipe that will be under pavement must be installed prior to paving. Failure to coordinate paving schedule with project manager could result in additional charges to the applicant.
- Applicant is responsible for providing utility easement, which may require obtaining 3rd party or disinterested party easements.
- Applicant is responsible for clearing path for OG&E facilities.
- Applicant must have the property pinned and to final grade prior to OG&E staking the job for construction. If grade is changed after construction is complete and causes OG&E to relocate facilities, Applicant must pay for 100% of relocation costs.
Applicant acknowledges that they have read and have been advised of all requirements. Oklahoma Applicant is aware of Title 63 Oklahoma Underground Facilities Damage Act (1991), Section 142.1, et. seq. (One-Call Statute, 8-1-1) prior to beginning any excavation or demolition pursuant to the provisions of this act. Arkansas Applicant is aware of Title 14-271-101 (One-Call Statute, 8-1-1) Arkansas Underground Facilities Damage Prevention Act prior to beginning any excavation or demolition pursuant to the provisions of this act.
Construction Standards
Number
Category
Title
U763.01
Distributed Energy Resources Standards
D732.31
Single Phase Commerical and Industrial
U762
Single Phase Commerical and Industrial
U773.10
Single Phase Commerical and Industrial
U773.2
Single Phase Commerical and Industrial
U773.7
Single Phase Commerical and Industrial
U773.8
Single Phase Commerical and Industrial
U773.10
Three Phase Residential Standards
U704
Single Phase Residential Standards
U762
Single Phase Residential Standards
U773.10
Single Phase Residential Standards
D727
Three Phase Commercial and Industrial Standards
D732
Three Phase Commercial and Industrial Standards
D732.31
Three Phase Commercial and Industrial Standards
U762
Three Phase Commercial and Industrial Standards
U762.3
Three Phase Commercial and Industrial Standards
U762.4
Three Phase Commercial and Industrial Standards
U765
Three Phase Commercial and Industrial Standards
U772
Three Phase Commercial and Industrial Standards
U773.10
Three Phase Commercial and Industrial Standards
U773.11
Three Phase Commercial and Industrial Standards
U773.12
Three Phase Commercial and Industrial Standards
U773.2
Three Phase Commercial and Industrial Standards
U773.7
Three Phase Commercial and Industrial Standards
U773.8
Three Phase Commercial and Industrial Standards